Skip to main content

Penetrating the Air Barrier.

Dealing with penetrations in the air barrier has definitely been a source of stress during this project.  Although my plans contain the penetration details, implementation of those details is pretty much left to me; unless I decide that I need help and in which case I would call Passive Design Solutions.  Some penetrations through the air barrier needed careful thought and planning before jumping in otherwise you could risk the integrity of the air barrier and fool up the insulation in the wall cavity all in one shot.  There are 5 wiring penetrations to the outside:  3 receptacles and 2 lights (well there is actually 3 light circuits but two which were more worrisome than others.)

Mounting the light/receptacle blocks to the exterior of the building could have been a mess if there was no foresight.  It is hard to attach a trim block to a foam wall.  The only solution was blocking attached to the studs directly behind the foam in the wall before the cavities were insulated.  I used 2x6 stud lumber for that that purpose.  It had to sit flush against the foam and had to be thick enough so that the siding would be just flush with the front of the block.  I drilled 4 counter sunken holes:  one in each corner and attached the block through the foam with 6" screws into the wall blocking.   Once the siding is finished and the electrical elements are installed I will install a small plug in each hole.  Without some thinking ahead, this would have caused a lot of headaches.

The plans called for a piece of conduit to be routed through the exterior 2x8 wall and into the electrical boxes.  The exterior perimeter of the conduit would be sealed to the OSB at the interior. using tape and acoustical sealant.  Once the wire is routed through the conduit it will be filled with spray foam.  The detail looks fine on paper.  However, drilling through a wall with fibreglass insulation is an uncertain task.  Fibreglass has a bad habit of wrapping around anything spinning so we came up with the following procedure.

1. Drill a 1 1/8" hole through the exterior block on the wall
2. Drill through the 3" foam slowly until the bit breaches through the back of the foam and the fibreglass is visible.
3.  Insert the 3/4" conduit (O.D. 1 1/8) from the outside and compress the insulation against the exterior side of the interior OSB. (my experience is that you can drill a hole through compressed insulation)
4.  Insert a long 3/4" spade it into the conduit and push it through until you feel the insulation at the end of the conduit
5.  Quickly drill until the tip spade bit just pierces the interior OSB.
6.  From the interior, drill the piloted hole with a 1 1/8" spade bit until it just passes through the OSB.

After removing the conduit, the hole was inspected with a small flash light.  The insulation was still filling the cavity and the hole left behind is large enough to pass the 3/4" conduit through the hole drilled in the wall and the conduit.  Although the hole was drilled with a 3/4"bit, there is enough give in the insulation that a 1 1/8 conduit easily passes through with careful direction.  After drilling is complete, the opening for the receptacle is cut with a jig saw (receptacle) or a hole saw (octagon box for a light).  The conduit is glued to a 3/4" threaded section, passed through the electrical box and secured with a locking screw.  The box/conduit assembly is the inserted into the opening in the trim block and secured with some screws.  At the interior conduit was caulked to the OSB using acoustical sealant.  A tape gasket was made with 3M All Weather Flashing tape and pushed back into the acoustical sealant.  The gasket was taped around the conduit for an air tight installation.  Once the wiring is installed, the conduit will be filled with spray foam.  Photos 1-1 through 1-8 illustrate the process.

The original design for the house called for an interior stove pipe.  The main reason for choosing an interior installation is performance.   Warm chimneys perform better.   After lighting a stove, bouyant gases rise through the flue pipe and deposit energy inside the chimney raising its temperature. Expanding gases move up the chimney and eventually spill out the top of the pipe.  As the chimney gets warmer this effect is more pronounced.  A pressure differential is created between the stove air intake and the chimney that causes draft.  Once draft is established it can be maintained by supplying heat.  When compared to an interior installation, a chimney installed outside needs more energy to establish and maintain an effective draft.  My internet searches really haven't provided any hard numbers regarding the amount of extra energy required.  Someday I may revisit this problem to see if there is some way to estimate the difference between the two scenarios.

Because of our floor plan, there was really one place to install the stove.  There were some uncertainties surrounding the interior installation that I was not happy about.These uncertainties played a large part in the decisions to move our stove.  The floor joist o.c. spacing, the proximity to the bedroom upstairs, having to create a chase in the middle of one of the bedroom walls, running the air intake under the slab, lack of an air tight installation, all added up to a complex problem that had a simple solution: move the stove to an exterior wall.   When passing through a combustable wall, a stove pipe requires a radiation shield (thimble).  The options for an air tight stove thimble in our marketplace are few and far between.  After some research, ICC (http://icc-chimney.com/) produces a thimble that can be used for an air tight installation.  Their EXCEL brand of chimney has a thimble (http://icc-chimney.com/en/excel, labeled on the web page as EWRSI).   The first time I saw a reference to this thimble was in a Green Building Advisor article.     The thimble required a framed opening of 10" x 10" and can fit into a wall with a thickness of 12" or less.  A decorative telescoping section can be used to ensure that the stove pipe exits the assembly 4" beyond the wall.  Our exterior wall is about 10 3/4" when the foam and OSB are included so rough framing had to be extended through the wall.  Due to the wall needing a 2x4 (on face) wiring chase, the stove thimble had to be offset from the wall 1" bandsaw pine frame in order for our cladding material (ship lap board) to work out. Photos 2-1 through 2-5 illustrate the installation.

Photo 3-1 illustrates the current state of the home....starting to look red!

Photo 1-1. Trim block marked for drilling.  Initial holes drilled for the final cut out with a jig saw.


Photo 1-2. Drilling through with a 1 1/8" bit.


Photo 1-3. Hole drilled through the trim block and just through the 3" of EPS foam.


Photo 1-4. Conduit inserted and pushed all the way to the interior OSB.  The conduit was used to pilot a 3/4" bit through the interior OSB


Photo 1-5. Once the tip of the 3/4 bit could be seen penetrating the interior surface, a 1 1/8" bit was used to finish drilling the hole from the inside.


Photo 1-6.   The conduit was attached to the receptacle box by gluing a threaded coupler and securing the assembly to the box using a locking nut.  The assembly was inserted into the cut out from the outside and slowly pushed through the wall to the interior.  The conduit will be sealed to the OSB with acoustical sealant and 3M tape.


Photo 1-7.  Electrical Box installed.  Once installation was complete it was taped over with tuck tape to preven water from getting into the wall assembly.


Photo 1-8. Conduit caulked and sealed with a home made 3M gasket.


Photo 2-1. View of the thimble rough stud opening from the perspective of our porch


Photo 2-2.  Insulated fire stop test fit.


Photo 2-3. Acoustical sealant caulked on the OSB around the opening for the insulated fire stop.


Photo 2-4. Pine frame and thimble/black telescoping section inserted through the rough stud opening (view from porch).  Gaps between the thimble and the rough stud opening can be filled with fireproof insulation before installing the insulated fire stop from the inside.  I stuffed Roxul into the cavity.


Photo 2-5.  The insulated firestop was pressed into the opening and nailed  to the OSB with drywall nails through pre-drilled holes in the galvanized plate.  The plate was initially placed on the wall and the hole location were marked.  A small dab of caulk was placed on the wall at the hole location so the nail would be air sealed to the galvanized plate.   The whole assembly will be air tight once the black section is caulked to the galvanized plate during final installation of the stove.


Photo 3-1.  The current state of the house.  Siding installation in progress.


Comments

Popular posts from this blog

Building the Air Tight Barrier: Door Flashing Details.

It took us a while to wrap our heads around the door details on my plans.  The main exterior wall is composed of 2x8s.  The rough stud opening was substantially larger than the door.  Because the walls are much deeper than a standard door frame for a 2x6 wall, the interior of the 2x8 opening was studded with double 2x4s.   Outside of these 2x4s, there is 1.5" of foam and another 2x4 on face which brings the door frame opening flush to the exterior 3" of EPS foam.  The brick mould of the door will sit against the exterior of the wall.  The ganged 2x4s which define the opening will allow the door to open a little further than that of a 2x8 wall.    With the door details finalized, I had to flash the opening as per the plan.  I specified the size/shape for aluminum sill pans and CBS Eavestroughing made them for me.  The sill pans have a kind of end dam to prevent water from entering under the under the stud opening should the door ever leak. (Photo 1-1).   After verifying t

Choosing an HRV...My Thoughts....

So, which HRV do you want for your home?  This is a question not often asked by the homeowner.  When the house is built, somebody installed an HRV and that was it.  The home owner is rarely involved in anything other than turning a knob on the HRV wall control if they dare fool with it at all.  An HRV is probably one of the most important appliances in your house;  it expels moisture, eliminates odours, evacuates stale air from bathrooms, provides clean air to keep you healthy and it recovers a lot of heat that would have otherwise been blown out through the vent on the house.  It serves three main functions: 1.  Supplies the home with fresh dry air. 2.  Removes stale air and removes excess moisture. 3.  Recovers heat or heat/moisture For a low energy home we need an HRV that is as efficient as possible.  With the ventilation unit taking care of exchanging most of the air in the building, having an efficient one will pay for itself in the energy saved over it's lifetime.  Zeh

Introducing: The Flatrock Passive House

So...after 8 1/2 years in our home, we have decided to move on.  Well, not right away! We have quite a bit of planning ahead of us.  With the likely onset of a 233% hike in the cost of electricity from Muskrat Falls (when compared to todays rate of $0.0972/kWh) we decided it was time to take energy consumption seriously before its too late to do anything about it.  The land has been acquired, the planning has started!  I am planning on nipping my energy bill in the bud before it becomes a major sinkhole in my pocket book. Upon investigating current building standards, I realized that the Canadian Building Code is below the standards necessary to really make a difference in energy consumption.  There are some standards like R2000 which can make a difference to total energy usage.  A R-2000 home can use up to 50% less heating energy compared to a code built home; if built properly!  A blower door test will reveal the truth about that. Now....Imagine living in a home where you have em