Skip to main content

A Well Insulated Slab.

After backfilling and infilling the the frost wall foundation, we tamped the fill material with a large reversible diesel compactor in hopes that it would lead to less issues with settling and therefore cracks in the slab over time.  These compactors are quite effective.  Material which would seem to be solid starts to collapse as it moves over the ground.  After compacting the garage (Photo 1-1) we moved on to compacting the the rock fill inside the house foundation Photo (1-3).  We had to leave a section open so the provincial electrical inspector could inspect the electrical conduit entering the house to ensure that it all met the code requirements.

Prepping for the slab insulation was fairly simple.  Our slab will be poured to a thickness of about 4" and the insulation is 10" of top II EPS foam.  We snapped a chalk line on the interior insulation, 14" below the top of the foundation, to use as a guide for filling the foundation with 3/4 crushed stone.  Slugging stone by hand is slow and heavy work.  We hired Weir's Construction to take care of spreading most of the stone using a stone slinger.  The slinger operator was able to distribute the stone fairly evenly.  However levelling the stone base before adding the foam sheets still requires some work.  Our reference chalk line for the 3/4 stone was visible on the interior foundation wall so it was easy to establish the stone height at the edge of the foundation.  However, levelling the inside was a little more laborious.  Assuming the top of the foundation was level (and it was because we checked it!), we strung a series of lines across the foundation from side to side.  Using rakes, shovels, and a 1 m landscaping rake we levelled the stone under the line to match the height at the edge of the foundation i.e. 14".  My plumber, Melvin Way, made short work of the plumbing runs.  My dad and I had a few errands to run so I figured I would get pictures when I returned....but it was already done and covered!

Using a small plate compactor the stone was compacted (Photo 2-1, 2-2).  As we worked we raked out high spots and added stone to low spots checking the depth as we go.  After compacting it was on to foam.  The slab has one load bearing wall which supports the second floor but not the roof.  To keep things simple we added a thickened slab under that load bearing wall which will be reinforced with rebar. Under that "footing" is 6" of Type 3 EPS which has a higher compressive strength than the Type 2 EPS used on the foundation and under the remainder of the slab.  In Photo 3-1 you can see a section of foam in the middle of the slab protruding above the 4" foam surrounding it.  We snapped a chalk line across the ground to represent the centre of the thickened slab.  We then laid the 6" foam (2'x8' sheets) centered on that chalk line.  We first started laying 4" foam starting in either corner of the foundation, working towards the 6" foam "footing" (Photo 3-1 to 3-4).  Cutting around the penetrations is the most time consuming task.  I have found that the quickest way to cut these holes is to mark the position on the sheet and using a 1/2" spade bit drill a series of consecutive holes through the foam at regular intervals.  Use you fist to punch out the centre!  I figure its going to be filled with spray foam anyways so it doesn't have to be really neat.  It just has to fit around the pipe and spray foam will do the rest.  After the first 4" layer is complete, we moved on to laying the next 2" layer in the same manner.  Once it came time to cut holes and fit pieces, one person did the cutting and another person moved on to laying more 4" foam.  It was ended with such a beautiful day that we decided to keep working.  At 8:45 pm we threw in the towels...well not really!  We had no option since we had used all of our 2" EPS!

Laying the foam took about 7.5 hours and we expect another 3 tomorrow to finish laying the foam.  We secured the foam for the night by laying 2'x4" lumber on top and rebar that I had on site.  You never know when its going to get windy!

Photo 1-1  After compacting the fill for the garage slab, my father looks onwards to the next task at hand.....compacting the house foundation!


Photo 1-2.  Moving a large compactor is easy!  You just need the right equipment to do it!


Photo 1-3 With the garage compacted it was time to move on to the house.  A portion of the house was left unfilled until the electrical inspection was complete.


Photo 2-1. Compacting the 3/4 stone before adding the foam insulation


Photo 2-2. Me taking a shift on the compactor.  You can see that the height of the stone around the foundation is pretty even.


Photo 3-1 Laying the first 4" layer.


Photo 3-2. laying the second 2" layer.


Photo 3-3. Laying the last 4" layer.


Photo 3-4.  Ran out of 2" Foundation Plus!!!





Comments

Popular posts from this blog

Building the Air Tight Barrier: Door Flashing Details.

It took us a while to wrap our heads around the door details on my plans.  The main exterior wall is composed of 2x8s.  The rough stud opening was substantially larger than the door.  Because the walls are much deeper than a standard door frame for a 2x6 wall, the interior of the 2x8 opening was studded with double 2x4s.   Outside of these 2x4s, there is 1.5" of foam and another 2x4 on face which brings the door frame opening flush to the exterior 3" of EPS foam.  The brick mould of the door will sit against the exterior of the wall.  The ganged 2x4s which define the opening will allow the door to open a little further than that of a 2x8 wall.    With the door details finalized, I had to flash the opening as per the plan.  I specified the size/shape for aluminum sill pans and CBS Eavestroughing made them for me.  The sill pans have a kind of end dam to prevent water from entering under the under the stud opening should the door ever...

Choosing an HRV...My Thoughts....

So, which HRV do you want for your home?  This is a question not often asked by the homeowner.  When the house is built, somebody installed an HRV and that was it.  The home owner is rarely involved in anything other than turning a knob on the HRV wall control if they dare fool with it at all.  An HRV is probably one of the most important appliances in your house;  it expels moisture, eliminates odours, evacuates stale air from bathrooms, provides clean air to keep you healthy and it recovers a lot of heat that would have otherwise been blown out through the vent on the house.  It serves three main functions: 1.  Supplies the home with fresh dry air. 2.  Removes stale air and removes excess moisture. 3.  Recovers heat or heat/moisture For a low energy home we need an HRV that is as efficient as possible.  With the ventilation unit taking care of exchanging most of the air in the building, having an efficient one will pay for itself...

Introducing: The Flatrock Passive House

So...after 8 1/2 years in our home, we have decided to move on.  Well, not right away! We have quite a bit of planning ahead of us.  With the likely onset of a 233% hike in the cost of electricity from Muskrat Falls (when compared to todays rate of $0.0972/kWh) we decided it was time to take energy consumption seriously before its too late to do anything about it.  The land has been acquired, the planning has started!  I am planning on nipping my energy bill in the bud before it becomes a major sinkhole in my pocket book. Upon investigating current building standards, I realized that the Canadian Building Code is below the standards necessary to really make a difference in energy consumption.  There are some standards like R2000 which can make a difference to total energy usage.  A R-2000 home can use up to 50% less heating energy compared to a code built home; if built properly!  A blower door test will reveal the truth about that. Now....Imagine ...